Preservation Projects · From the Winter 2006 archive
Preparing Old St. Mary’s for a Wet Winter
Wiring, insulation, wall protection, and a new bell tower moved the rescue forward.

Saving Old St. Mary’s required more than moving it out of danger. The old building also had to withstand another winter while volunteers worked toward a new use.
Gene Johnson’s Winter 2006 report described completed wiring, foam insulation, wall sheathing, and protective house-wrap. Sparse early rains had given the crew time to make progress.
Clues inside the framing
The exposed structure suggested that arched windows had originally been intended, although rectangular windows had been installed. The restoration plan called for arched tops, with individual sponsors helping meet the cost.
Dave Ruhkala and other carpenters built the base for the bell and new steeple. Community Covenant Church supplied a loaned bell with its own Rocklin history.
Practical needs behind the landmark
Engineering plans also addressed the annex, which would hold a restroom, work space, utilities, and heating and cooling equipment.
These less visible parts of the project mattered as much as the steeple. Together they would allow a rescued nineteenth-century building to function as a comfortable community venue.